PASSER installation of a 150t Carousel on the Philippines was successfully carried out first week of November!

The carousel will be storing HVAC 230kV single core cables in connection with the CNP-3 cable interconnection project between Talavera to Calatrava.

This system is particularly suitable for an easy and quick setup world wide. The carousel is designed and built in sections for container transport with bolted connections for steel units and drive system.

Our team completed the assembly and test well ahead of scheduled time, in just 4 days.